Project Description
Swietelsky Rail Australia (SRA) has been the exclusive provider of mechanised ballast cleaning services for the Australian Rail Track Corporation (ARTC)'s Heavy Haul Hunter Valley network since 2014.
February 2025 Swietelsky Rail Australia (SRA) officially kicked off our first major project program for 2025! The Swietelsky Rail Australia (SRA) team successfully delivered full ballast replacement, ballast cleaning and corridor improvements across a 9km project site at Muswellbrook, NSW for our valued client Australian Rail Track Corporation (ARTC).
In just 72 hours, we delivered our fence-to-fence approach to corridor betterment, including mechanised maintenance, and rail & civil asset improvements. This included safe and successful completion of: